Glossary entry

Chinese term or phrase:

后浇带

English translation:

(Delayed) pour strip

Added to glossary by Frank Zou
Jan 26, 2019 07:11
5 yrs ago
2 viewers *
Chinese term

后浇带

Chinese to English Other Construction / Civil Engineering 土木工程
Is there an equivalent term in English?

后浇带是在建筑施工中为防止现浇钢筋混凝土结构由于温度、收缩不均可能产生的有害裂缝,按照设计或施工规范要求,在基础底板、墙、梁相应位置留设临时施工缝,将结构暂时划分为若干部分,经过构件内部收缩,在若干时间后再浇捣该施工缝混凝土,将结构连成整体。后浇带的浇筑时间宜选择气温较低时,可用浇筑水泥或水泥中掺微量铝粉的混凝土,其强度等级应比构件强度高一级,防止新老混凝土之间出现裂缝,造成薄弱部位。设置后浇带的部位还应该考虑模板等措施不同的消耗因素。

Proposed translations

17 hrs
Selected

(Delayed) pour strip


"A pour strip, or delayed pour strip, is a section of slab left open during the initial concrete placement,."


https://www.post-tensioning.org/Portals/13/Files/PDFs/Public...

"Delayed pour strips are strips in a slab of concrete which are left as empty gaps when the concrete is first poured and then filled in later in a second pouring when the first pouring has dried"

https://www.proz.com/kudoz/english/construction-civil-engine...
Something went wrong...
4 KudoZ points awarded for this answer.
2 hrs

post-cast strip

FYI
Note from asker:
Doesn't seem right....Literally, "post-cast" means after concrete is cast, but here 后 means "later"
Something went wrong...